Development projects

What the company is renewing right now: the trolleybus contact network, the depot grounds, the charging and gas filling infrastructure. Each project shows what is already done and what is still ahead.

Clean Sky: the contact network

Stage · Design wrapping up, construction starts in October 2026

The trolleybus contact network is being rebuilt on seven Almaty streets. Poles and wires are replaced in full, the feeder cables go underground, and the street lights move onto the same poles. The rest of the network keeps running as usual.

Clean Sky: the contact network
A design solution, not a photograph of completed work
  • Seven streets in the first stage, 19.82 kilometres of line
  • Roughly a tenth of the city trolleybus network
  • 980 steel poles 11 metres tall, replacing worn concrete ones
  • The failing 600 V feeder cables move underground
  • Energy efficient LED luminaires mounted on the same poles
  • Nine months of work, and a 30 year service life for the new network

The square at Almaty-1 station

Stage · Design solution

The overhead line poles by Almaty-1 station are being replaced. The poles, wires and suspension hardware that come down are reused rather than scrapped.

The square at Almaty-1 station
A design solution, not a photograph of completed work
  • Three sections: the square itself, the stretch by the station facade and the pedestrian crossing
  • The dismantled equipment is reinstalled on three sections of Momyshuly Street
  • The square is not part of the first stage of Clean Sky

Repairs to the depot grounds

Stage · Partly done, partly in design

The surface of the driveways, the parking areas and the gas filling zones is being replaced: two layers of asphalt concrete, kerbstone and road markings.

Repairs to the depot grounds
  • Depot No. 1: 2,535 square metres, work completed
  • Depot No. 2: about 0.8 hectares, work completed
  • Depot No. 3: about 0.8 hectares, still in design

Charging infrastructure

Stage · In operation

Depot No. 5 is the only site of the company where electric and gas buses work side by side. The charging stations stand on its territory.

Charging infrastructure
  • Five My Charge stations of 160 kW
  • Two electric buses charge in four hours
  • Two electric bus routes: No. 90 and No. 124
  • Electric buses produce zero harmful emissions

Gas filling stations

Stage · In operation

Gas buses are filled on the depot grounds, at night and between shifts.

Gas filling stations
  • Depot No. 2: an own Aspro station, four compressors, 4,000 m³ per hour
  • Depot No. 3: a private station, four dispensers, 5,000 m³ per hour